Fingal County Council have clearly shown a laudable commitment to innovation by introducing a mandatory planning requirement for seven areas that all new developments reduce energy use and C02 emissions relating to space & water heating to 60% below Building Regulations requirements, with 30% of space & water heating coming from renewable energy sources
|
|
Read More >>
|
Latest Blog Comments
Official magazine of Easca 
|
|
A Lesson in Energy Efficiency |
|
Page 1 of 6
The
Department of Education has made its commitment to energy efficiency
and CO2 reduction clear in developing and bringing into practice
targets for primary school design that aim for less than half of the
accepted good practice in the field. Project coordinator John Dolan, Senior Engineer with the Department of Education
explains how this approach works within normal Departmental budgetary
limits to create school buildings that show the way ahead for building
designers.
The commitment of the Planning and Building Unit within the Department of Education & Science to developing low energy educational buildings continues with the roll out of generic repeat design (GRD) schools.
The project is one of many of the energy projects that the Planning and Building Unit continue to develop as part of their energy policy which is based on a process called the DART approach. The acronym focuses on four key areas, namely; Design, Awareness, Research, and Technology.
The objective of the generic repeat design process was to develop an off the shelf solution to pre-tender stage for a template primary school design package that can be given to design teams. The design team then deals with site specific issues, the planning process and tendering and construction. A key advantage of this is savings in significant design time and costs as the generic design emphasis means that new permanent primary school accommodation can be provided in approximately fifteen months from need identification, site procurement and design team appointment.
The GRD school project consists of a design for a standard eight, twelve, and sixteen classroom school built in line with the Department’s basic building cost but with additions for air tightness and improved insulation standards. The design also allows for the eight and twelve classroom versions to be expanded in the future if needed with minimal disruption to the existing school building whilst allowing the day to day functions of the school to continue.
The design is a two storey solution which maximises land-use, provides a compact building envelope that can be easily extended, and offers the benefits of improved security, supervision and inter-relationship of spaces for the school management team and users. The building has been designed with reference to best practice in school design with emphasis on all aspects of the learning environment, creating a whole building solution, and addresses issues such as massing, orientation, spaces, use of durable and low-maintenance materials, sustainability, access for all and integration of special needs pupils, with clear way-finding definite entrances and an alternative main entrance to suit a variety of site orientations.

The School's atrium allows daylight penetration
The layout is centred on an atrium area with the main teaching spaces organised along the east and south elevations to maximise passive solar gain and natural daylighting for the hours of use. Ancillary accommodation is distributed on the other two orientations including the general purpose hall with internal glazing permitting viewing to and from an upper level balcony corridor into the hall thus giving a sense of transparency and inclusiveness along with facilitating passive supervision.